Portlet: Tasks in Project
This portlet shows summary information about tasks assigned to users.
Status Color Codes
The colors of each task indicate the execution status:
- Blue - Not started yet:
The task will start in the future, so there are no actions planned as of today.
- Green - In process (OK):
The task has started and is being completed as planned. The actual done % corresponds to the value planned for today.
- Yellow - In process (late):
The task has started, but it has not been completed according to the plan, or the project manager did not yet update the status...
- Red - Late:
The task should have been finished already, but the done % is not yet 100%.
- Grey - Finished:
The task has been finished, done % is 100%.
- Purple - Undefined:
The system can not calculate the execution status.
This can happen if a task has not start- or end-date due to incomplete data-entry or similar situations.